Most people have never had solar fitted, so installation day is a bit of an unknown. Here’s what happens on a typical Lumen home installation, in order. Most home jobs are finished in a day; bigger systems, or ones with extra electrical work, can take two.
Before the day
By the time our installation team arrives, a few things are already done:
- The survey and design. We’ve looked at your roof, your fuse board and where the inverter and battery will go, and you’ve signed off a design that names every part.
- Your SEAI grant offer. For the grant, nothing can be installed until your offer is in place. We help you through that application first.
- ESB Networks approval. We submit the NC6 form to ESB Networks, and it must be approved before we install.
- A date that suits you. You’ll know roughly when the crew arrives and how long they expect to be there.
What helps on the day:
- Clear a path to the attic hatch and the fuse board.
- Move the car if it’s in front of the wall where the inverter is going.
- Keep the Wi-Fi password handy. The inverter connects to it so the app works.
Morning: up on the roof
The crew sets up safe roof access first. Then they:
- Fix the mounting rails to the rafters with roof hooks, lifting and re-seating tiles or slates around each one so the roof stays weathertight.
- Lay out and fit the panels on the rails, to the layout in your design.
- Run the cables from the panels into the attic, neatly secured.
Midday: the electrical work
While the panels go on, a registered electrician works inside:
- Mounts the inverter, and the battery if you’re having one, usually in the garage, a utility room or on an outside wall.
- Runs and connects the cables between the panels, the inverter and the fuse board, with the isolation switches that make the system safe to work on.
- Connects into your fuse board with its own protection. Your power may be off for a short time during this part. We’ll tell you before it happens.
Afternoon: switching on
Then the system is commissioned:
- Tested and measured, with the results recorded.
- Switched on, with the first output showing on the inverter.
- Your app set up on your phone, with a walk-through of what the screens mean and, if you have a battery, how it’s set to charge and discharge.
- The site tidied, and packaging taken away.
After the day
A few things follow on behind the scenes:
- The post-works BER assessment. The SEAI grant needs one after the installation. Your BER assessor visits, and the new rating usually improves with solar.
- The grant claim. Once the paperwork and BER are in, the claim goes to SEAI, which pays the grant to us. You have already had it deducted from your price.
- Your export payments start once your supplier has your details. See getting paid for the power you export.
And after that
We don’t disappear. If something on the app looks wrong, contact us and we’ll look at your system’s data. Many problems can be sorted remotely without anyone calling out.
Ready to book yours? Start with a free site survey, or read how the whole process works.